工地鋼筋加工棚的定做要注意什么?
來(lái)源:http://www.perthama.com/ 發(fā)布時(shí)間:2023-07-24
鋼筋加工棚是施工現(xiàn)場(chǎng)內(nèi)對(duì)鋼筋進(jìn)行拉直、彎曲、焊接等鋼筋加工作業(yè)的一個(gè)場(chǎng)地。鋼筋加工棚的長(zhǎng)和寬,一般會(huì)根據(jù)鋼筋加工數(shù)量和使用機(jī)械的多少確定加工棚的大小,一般情況有6*12m、9*12m、18*30m等幾種,可以根據(jù)施工實(shí)際情況,自行設(shè)計(jì)長(zhǎng)與寬尺寸。鋼筋加工棚工作臺(tái)的布置也要合理,根據(jù)真實(shí)鋼筋加工流程來(lái),還有加工前原材料鋼筋和加工結(jié)束后成品的存放,所以鋼筋加工棚的地面應(yīng)高于施工場(chǎng)地地面30cm,防止雨水浸泡,用腳手管進(jìn)行搭設(shè)時(shí),應(yīng)有地橫桿和斜撐,以保證加工棚的穩(wěn)定性。
The steel bar processing shed is a site for straightening, bending, welding, and other steel bar processing operations on the construction site. The length and width of the steel bar processing shed are generally determined based on the number of steel bars processed and the amount of machinery used. Generally, there are several types of processing sheds, such as 6 * 12m, 9 * 12m, and 18 * 30m. The length and width dimensions can be designed according to the actual construction situation. The layout of the workbench of the reinforcement processing shed should also be reasonable, according to the real reinforcement processing process, as well as the storage of raw material reinforcement before processing and finished products after processing, so the ground of the reinforcement processing shed should be 30cm higher than the ground of the construction site to prevent rain soaking. When erecting with scaffold tubes, there should be ground cross bars and slant support to ensure the stability of the processing shed.
二、工地鋼筋加工棚定做:
2、 Customized steel bar processing shed on the construction site:
施工現(xiàn)場(chǎng)鋼筋加工棚采用國(guó)際標(biāo)準(zhǔn)鋼材制作,在現(xiàn)場(chǎng)利用扣件將多根鋼管扣接搭設(shè)成加工棚的整體式鋼結(jié)構(gòu),再設(shè)置斜撐和雙層防砸結(jié)構(gòu),校驗(yàn)鋼結(jié)構(gòu)強(qiáng)度是否符合設(shè)計(jì)要求,后在欄桿上鉤掛標(biāo)語(yǔ)橫幅,整個(gè)鋼筋加工棚施工完畢標(biāo)準(zhǔn)化設(shè)計(jì)。全拼裝式,快速組裝,拆卸簡(jiǎn)單,方便運(yùn)輸,型材及配件規(guī)格可按需求來(lái)定制。同時(shí)地面也需要硬化,立柱基礎(chǔ)澆筑700*700*700mm混凝土,預(yù)埋300*300*12mm鋼板。
The reinforcement processing shed at the construction site is made of international standard steel. First, multiple steel pipes are buckled and erected into an integral steel structure of the processing shed at the site with fasteners, then slant support and double-layer anti smashing structure are set to verify whether the strength of the steel structure meets the design requirements, and finally, safety banner is hooked on the railing, and the standardized design of the entire reinforcement processing shed is completed. Fully assembled, quick assembly, easy disassembly, and convenient transportation. The specifications of profiles and accessories can be customized according to needs. At the same time, the ground also needs to be hardened, and the column foundation is poured with 700 * 700 * 700mm concrete, and 300 * 300 * 12mm steel plates are embedded.
三、工地鋼筋加工棚廠家:
3、 Manufacturer of reinforcement processing shed on construction site:
1.一般情況下,鋼筋加工棚都在塔吊的吊運(yùn)范圍內(nèi),否則鋼筋吊動(dòng)不方便,同時(shí)必須設(shè)置雙層硬質(zhì)防護(hù),棚的具體尺寸要根據(jù)實(shí)際情況來(lái)定。
In general, the steel bar processing shed is within the lifting range of the tower crane, otherwise it is inconvenient to lift the steel bars. At the same time, double layer hard protection must be installed, and the specific size of the shed should be determined according to the actual situation.
2.防護(hù)棚的頂有二層的,上面的隔層上鋪模板,下面一層鋪二層竹芭片子,二層之間間距500 mm。
2. The top of the protective shed has two layers. The top partition is covered with formwork, and the bottom layer is covered with two layers of bamboo sheets, with a spacing of 500 mm between the two layers.
3.工具式鋼筋加工棚需在醒目處掛操作規(guī)程圖牌和宣傳用語(yǔ)的橫幅,圖牌的尺寸為:寬×高=2000mm×1000mm,橫幅寬度宜為1m。
3. The tool type steel bar processing shed should be prominently hung with operating instruction signs and safety propaganda banners. The size of the signs is: wide × Height=2000mm × 1000mm, the width of the banner should be 1m.